Question: 1 / 190

Your management is applying the 10 percent solution: It has requested that you reduce the budget for the project which you are currently initiating by 10%. What will this probably mean for your project?

?

If the project budget is an honest one, then a reduction in budget must be accompanied by a trade-off in either time or performance.